Support deadline · SAP

SAP PI/PO end of support: your options and timeline

SAP PI/PO 7.5 mainstream maintenance ends at the end of 2027 (we count to 31 December 2027): 453 days remaining (SAP: Process Integration way forward (SAP blog), checked on 2026-10-03).

SAP PI/PO end of life comes in two steps. SAP describes Process Integration 7.5 as available "until 2027 on standard maintenance and 2030 for extended maintenance" (SAP: Process Integration way forward (SAP blog), checked on 2026-10-03), and extended maintenance for NetWeaver 7.5 runs to the end of 2030 at extra cost (SAP: NetWeaver maintenance strategy, checked on 2026-10-03). SAP names SAP Integration Suite as the logical successor.

Last updated . Figures are re-checked quarterly.

The PI/PO timeline

DateWhat happensSource
End of 2027Mainstream maintenance for SAP PI/PO 7.5 ends.(SAP: Process Integration way forward (SAP blog), checked on 2026-10-03)
End of 2030Extended maintenance for SAP NetWeaver 7.5, the platform PI/PO 7.5 runs on, ends; it carries a premium of two percentage points on the maintenance basis.(SAP: NetWeaver maintenance strategy, checked on 2026-10-03)

Your options

How long it takes

SAP gives indicative durations: landscapes of up to 100 interfaces that are mostly lift-and-shift "commonly take 1–3 months"; up to 300 interfaces take three to six months; large landscapes can take more than a year (SAP: FAQ, migration from Process Orchestration to Integration Suite, checked on 2026-10-03). SAP describes two approaches: lift-and-shift with minimal functional change, or modernization toward API-led and event-driven patterns (SAP: FAQ, migration from Process Orchestration to Integration Suite, checked on 2026-10-03). Lift-and-shift is faster; modernization is the chance to retire interfaces nobody needs.

Measured against the deadline, the arithmetic is tight for large estates. A landscape of 300 interfaces at SAP's indicative pace needs three to six months of migration work, before testing with partners, cut-over windows and the year-end freezes many SAP customers observe. Starting a year ahead of the end of mainstream maintenance leaves room for one slipped wave; starting six months ahead does not.

Migration-readiness checklist

Disclosure: iPaaS Tools offers migration tooling and services, so we have an interest in this topic. We have no affiliation with, and are not endorsed by, any vendor named here; product names belong to their owners.